*Please note – at this time all dates are estimated and subject to change, unless noted as "CONFIRMED".  Please stay tuned for public notices.


schedule1.jpg

  • Local Special Use Permit Complete: November 2021
  • Preliminary Interconnect Results: January 2022
  • Environmental and Other Studies: October 2021-July 2022
  • Full Interconnect Results: September 2022
  • State and Federal Permitting: First Half 2022
  • Interconnection Facilities Construction: Q1 2023- Q3 2024
  • Construction Start (Phase I): Q2 2023
  • Construction Start (Phase II): Q4 2023
  • Construction Complete (Phase I): September 2024
  • Construction Complete (Phase II): December 2025