Project Schedule
*Please note – at this time all dates are estimated and subject to change, unless noted as "CONFIRMED". Please stay tuned for public notices.
Local Special Use Permit Complete: November 2021
Preliminary Interconnect Results: January 2022
Environmental and Other Studies: October 2021-July 2022
Full Interconnect Results: September 2022
State and Federal Permitting: First Half 2022
Interconnection Facilities Construction: Q1 2023- Q3 2024
Construction Start (Phase I): Q2 2023
Construction Start (Phase II): Q4 2023
Construction Complete (Phase I): September 2024
Construction Complete (Phase II): December 2025